Tier1 and Tier-2 Weekly Report 2013-04-09
General News
- ADC and ATLAS Computing News [20130409]
- ADC Weekly meeting
- Start delayed due to topics in Open EB meeting
- Hammercloud Tests updates
- Athena versions used in current AFTs not compatible with SLC6 (affecting SARA)
- PFTs do not need to be updated, since no code is compiled on WN
- While updating, reduce AFTs from 4 to 3 (transparent)
- New AFT tests are healthy with similar performance (running since a week)
- Dataset replication ongoing (only needed for data12 test)
- Plan to switch as soon as all sites have necessary datasets (probably later this week)
- Some verbal discussion about few fixes needed in pilots for software tests and plans to run these in analysis pilots
- CA Cloud Squad Actions [20120626]
-
- other cloud squad related savannah and / or ROC ggus tickets [20110705]
- panda monitor for PD2P activity within clouds (default view (last 7 days) units = datasets)
- Open Issues and Ongoing Discussions
- Sites should be providing the April 2012 storage pledge.
- HammerCloud [20120214]
- gLite/EMI News [20121127]
- ROC_Canada News [20121030]
- Current shift - Neil Knecht November 5-9, 2012
- Next Week - Simon Nderitu
- WLCG and General Computing News [20120911]
SSB Results
- Critical tests for each site in the Site Status dashBoard are available at the links below
SSB PanDA Test Queue Availability (month)
- this metric, measured for the analysis queues, defines the site status for data preplacement as alpha (
T2D and avail > 90%), bravo (T2 and avail > 90%) or charlie (< 90%).
SAM Results
- site service status via Gridview
- Please check your site
- April 2012 Detailed Site Information (valid until 20120430):
- TRIUMF-LCG2
- Australia-ATLAS
- CA-ALBERTA-WESTGRID-T2
- CA-SCINET-T2
- CA-VICTORIA-WESTGRID-T2
- SFU-LCG2
APEL Accounting
- ACTION ITEM FOR SITES: Sites please regularly check and confirm that your historical APEL data has been published and looks correct when comparing with batch system utilization
APEL Publishing Status
APEL Accounting Results
APEL Synchronization Test Links
Site Reports
Alberta
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Victoria
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Toronto
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
McGill
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Australia-ATLAS
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
Outstanding Issues
Production
Summary
- NOTE: ARDA ProdSys Dashboard has stopped being used by ADCoS team due to information updating issues with the interface. The historical job usage information is to appear separately within ARDA and is being validated. This will be used in the future for information presented here.
- Within the CA Cloud and Worldwide (Panglia
View):
--
LeslieGroer - 2013-04-09